Leisure Improvement Works - Phase One
- Find out more about this issue
- Share this item
Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
The report’s purpose is to seek approval
for the appointment of a contractor to carry out the leisure
improvement works – phase one.
Decision:
Decision
That Cabinet:
1. Approves the contract award for the leisure improvement works at a cost of £321,222.00 to the preferred supplier Northdown Property Services (NPS) Limited, for a period of up to six months with the option to extend for a further six months if required.
2. Approve the allocation of a revenue budget from the Leisure Investment Reserve to fund the works.
3. Delegate authority to the Section 151 Officer, in consultation with the Cabinet Member for Leisure and Culture to extend the contract by up to a further six months and make any contract variations to the scope of should this be required.
Reasons for the decision
The contract with NPS Limited would ensure that the changing rooms were refurbished to a high standard and undertaken in accordance with agreed budgets, thus improving the customer experience across each of the three leisure centres and sports stadium.
A compliant procurement exercise was undertaken to identify a preferred contractor and following expiry of the appropriate standstill period the contract needed to be formally awarded.
Other options considered
The Council could have chosen not to undertake the phase one improvement works; however, this was discounted as the Leisure Investment Reserve has been established with the primary objective of improving the cosmetic appearance of each of the three leisure centres and sports stadium.
Report author: Michael Chester