Agenda item

Application S20/0908

Proposal:                  Erection of 3 detached houses

Location:                   Land Off Kettering Road, Stamford, Lincolnshire, PE9 2JS 

Recommendation:     That the application be approved conditionally

Minutes:

Proposal: Erection of 3 detached houses

Location:   Land Off Kettering Road, Stamford, Lincolnshire, PE9 2JS 

Decision:   To approve the application conditionally.

Noting:

·            Provisions within the National Planning Policy Framework, the South Kesteven Local Plan 2011 – 2036 and supplementary planning documents and the draft Stamford Neighbourhood Plan.

·            No objection from Stamford Town Council subject to any affordable housing contribution being allocated and spent in Stamford and neighbouring properties amenities being respected.

·            No objections from Lincolnshire County Council Highways and SuDS support.

·            Comments from Lincolnshire County Council – Footpaths Officers regarding Kettering Public Footpaths Nos 14 and 15 that would be affected by the proposed development.

·            No objections from the(LCC) Minerals and Waste Planning.

·            A recommendation from Heritage Lincolnshire for an archaeological investigation scheme to be secured by condition.

·            No objection from Peterborough City Council.

·            No objections but comment from Historic England suggesting that the views of specialist conservation and archaeological advisors are sought.

·            Objection from Wothorpe Parish Council, in respect of the site not allocated in the emerging Local Plan, harm to heritage assets including setting of Stamford not outweighed by public benefits, and highway safety.

·            Objections from Barnack Parish Council, in respect of site not allocated in emerging local plan, harm to heritage assets and harm to character of the area.

·            No comments from the Garden Trust.

·            Representations received as a result of public consultation.

·            Verbal update from the officer correcting a typographical error in Condition 9 of the proposed conditions.

·            Comments made by Members at the meeting.

 

Members commented on:

·            Whether a condition could be included regarding soft landscaping.

 

Condition 8 referred to soft and hard landscaping for the site.

 

·            The potential loss of heritage contained on site such as the kissing gates, other wrought iron furniture and, potential hidden heritage within the trees currently on site and potential harm to the conservation area.

 

The planning officer noted that a condition could not be included that sought to specify requirements for the public right of way, which would require consultation with LCC, but the Committee’s comments and suggestions could be incorporated in an advisory note encouraging the developer to investigate further and retain such objects.

 

·            How affordable housing would fit into this scheme.

 

In respect of affordable housing, the developer would contribute an amount of £258,572  to off-site extra-care affordable housing. This would be used as a contribution towards properties for the elderly on smaller sites that enabled independent living with a level of care.

It was proposed, seconded, and agreed that the application be approved for the summary of reasons set out in the case officer’s report, together with the following conditions:

Time Limit for Commencement

1      The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.    

Approved Plans

2      The development hereby permitted shall be carried out in accordance with the following list of approved plans:    

                   i.       Site location plan drawing no. 1980-200 A received 11 June 2020.

                 ii.       Block Plan drawing no. 1980-201 received 9 June 2020.

                iii.       Plot A floor plans drawing no. 1980-204 and 1980-205 received 9 June 2020.

                iv.       Plot A elevations drawing nos. 1980-206 and 1980-207 received 9 June 2020.

                 v.       Plot A garage drawing no. 1980-208 received 9 June 2020.

                vi.       Plot B floor plans drawing no. 1980-209 and 1980-210 received 9 June 2020.

              vii.       Plot B elevations drawing nos. 1980-211 and 1980-212 received 9 June 2020.

             viii.       Plot B garage drawing no. 1980-213 received 9 June 2020.

                ix.       Plot C floor plans drawing no. 1980-214 and 1980-215 received 9 June 2020.

                 x.       Plot C elevations drawing no. 1980-216 received 9 June 2020

                xi.       Plot C garage drawing no. 1980-217 received 9 June 2020.

       

Unless otherwise required by another condition of this permission.         

Before the Development is Commenced

3      Prior to the commencement of the development hereby permitted, a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the local planning authority. This shall indicate measures to mitigate against traffic generation and drainage of the site during the construction stage of the proposed development. The development shall then be carried out in accordance with the approved CEMP. The CEMP shall include, though not necessarily be restricted to, the following details:

a)   A site waste management plan.

b)   A Traffic Management Plan incorporating the routing of construction traffic and details of heavy vehicle patterns (including earliest and latest times and suspension of trips during peak traffic times).

c)   Measures to minimise and control noise, vibration, dust, and fumes during site preparation works.

d)   Details of the site parking of all vehicles of site operatives and visitors.

e)   The location, extent, and duration of any temporary stockpiling areas.

f)    Measures for wheel washing to prevent mud being deposited on the surrounding highway.

g)   Phasing of the development to include access construction.

h)   Loading/unloading of plant and materials used in constructing the development.

i)    Construction activities will not take place outside the hours of 08:30 to 17:30 Mondays to Fridays, or 09:00 to 13:00 on Saturdays, and will not take place at any time on Sundays or Bank/Public Holidays.

j)    A programme of implementation for items a) to i) above.

The approved CEMP shall be strictly adhered to throughout the construction period.

4      Prior to the commencement of the development hereby permitted, a tree protection method statement including protection plan shall be submitted to and approved in writing by the local planning authority. The method statement and plan should have regard to the BS5837 (2012) Trees in Relation to Design, Demolition and Construction – Recommendations. A plan identifying which trees are to be felled and which are to be retained should also be provided. A site-specific tree protection scheme for the retained trees should also be submitted taking into account the impacts from construction work, scheduling of works, foundations, hard surfaces, drainage systems and utilities.

            The approved details shall be strictly adhered to throughout the construction period.

5      No development to construct the dwellings shall take place until        details demonstrating how the proposed dwellings would comply with the requirements of Local Plan Policy SB1 have been submitted to and approved in writing by the local planning authority. The scheme shall include details of how carbon dioxide emissions would be minimised through the design and construction of the buildings, details of water efficiency and the provision of electric car charging points. The approved sustainable building measures shall be completed in full, in accordance with the agreed scheme, prior to the first occupation of the dwellings hereby permitted.

During Building Works

6      Before any of the works on the external elevations for the building(s) hereby permitted are begun, samples of the materials (including colour of any render, paintwork, or colourwash) to be used in the construction of the external surfaces shall have been submitted to and approved in writing by the Local Planning Authority.

 

7      Prior to the commencement of works on site, other than those works for site clearance, details of the disposal of foul and surface water drainage shall be submitted to and approved in writing by the local planning authority. The approved works shall be completed in accordance with the details and shall be provided prior to the first occupation of the development.

8        Notwithstanding the submitted plans, before the completion of any of the dwellings, details of a soft and hard landscaping scheme shall be submitted to and approved in writing by the local planning authority. The scheme shall include the following:

a)   Fully annotated plans showing the locations of individually planted semi-mature trees, shrubs, and hedging, which shall include planting schedules, noting species, plant sizes and proposed numbers and densities, method of cultivation and details of the proposed planting implementation programme.

b)   Details of the boundary treatments and finished site levels/contour details.

c)   Surfacing treatments of the pedestrian circulation areas, parking areas and paths.

Before the site is occupied

9      The landscaping details approved under condition 8 shall be implemented in the first planting season following first occupation of the development and individual plot landscaping shall be completed before the occupation of that housing plot. If, within a period of 5 years from its date of planting, any tree is uprooted, removed, or is destroyed or dies or becomes seriously damaged or defective, then a replacement tree of the same species and size as that originally planted shall be planted in the same position or another position approved by the local planning authority.

10    Prior to the completion of any of the dwellings, a scheme of the provision of bat and bird boxes shall be submitted to and approved in writing by the local planning authority. The boxes shall be installed prior to occupation and retained thereafter.

11    Prior to the first occupation of the development hereby permitted, a 1.8 metre footway to connect the development to the existing pedestrian footway on Kettering Road at Pinfold Lane shall be provided as part of application S18/1207 in accordance with details that shall first have been submitted to and approved in writing by the local planning authority. The works shall also provide details of the arrangements for the management of surface water run-off from the highway.

12    Before any part of the development hereby permitted is occupied/brought into use, the external surfaces shall have been completed in accordance with the approved details.

On-going conditions

13    Notwithstanding the provisions of Schedule 2, Part 1, Class A and Schedule 2, Part 2, Class A of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking or re-enacting that Order, with or without modification), no enlargement, improvements or other alterations and no gates, fences, walls or other means of enclosure to plots A, B and C shall be carried out without planning permission first having been granted by the local planning authority.

11:20 – 11:30 the meeting adjourned.