Grantham Meres Leisure Centre - Award of contract for decarbonisation works

Decision Maker: Deputy Chief Executive, Section 151 Officer

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To seek approval to award a contract for the installation and associated works of a low carbon heating system at Grantham Meres Leisure Centre utilising funding received from the Public Sector Decarbonisation Scheme (phase 3c).

Decision:

That approval is granted for a Development Management Agreement for decarbonisation works at Grantham Meres leisure centre is entered into with Alliance Leisure.

Publication date: 28/03/2025

Date of decision: 28/03/2025

Accompanying Documents: