Decision details
Wellington Way, Market Deeping - Approval of Contract Sum Increase
- Find out more about this issue
- Share this item
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
To increase the approved construction contract
sum for the Wellington Way new build housing scheme by
£190,000, following the findings of a recent site
investigation and technical report undertaken after contract
award.
To seek delegated authority to the Council’s Section 151
Officer, in consultation with the Leader of the Council, to approve
up to a further 10% additional funding should unforeseen costs
arise during delivery of the project.
Decisions:
Note: Councillor Philip Knowles returned to the Council Chamber.
Purpose of report
To increase the approved construction contract sum for the Wellington Way, Market Deeping new build housing scheme by £190,000. This was following the findings of recent site investigations, and technical reports undertaken after the initial contract award in September 2025.
Decision
That Cabinet approve an increase of £190,000 to the approved construction contract sum of £1.926m for the Wellington Way, Market Deeping new build housing scheme. This was due to additional works arising from recent survey findings.
Other options considered
Not approving the additional funding would have resulted in delays to the project and could have compromised delivery of the scheme. This option was discounted due to the ongoing housing need and the importance of maintaining the certainty of the programme.
Reasons for the decision
Approval of the additional funding enabled the Wellington Way scheme to proceed without delay, ensuring delivery of high-quality, sustainable council housing whilst protecting the Council’s investment.
Following the initial contract award, site investigations were undertaken which looked at ground conditions. Previously unknown areas of ground with historic contamination were discovered; this could not have reasonably been identified at the tender stage.
The works would be funded from HRA capital receipts.
Report author: Suniel Pillai
Publication date: 18/08/2026
Date of decision: 10/02/2026
Decided at meeting: 10/02/2026 - Cabinet
Effective from: 19/02/2026
Accompanying Documents: