Instruction of Pre-construction works at Swinegate, Grantham New-build housing development

Decision Maker: Chief Finance Officer, Section 151 Officer

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To seek approval to enter into a contract with Lindum for pre-construction phase works relating to HRA new build housing scheme at Swinegate, Grantham.

Decision:

That approval is granted to enter into a contract with Lindum for pre-construction phase works relating to HRA new build housing scheme at Swinegate, Grantham for a total cost of £197,703.21.

 

Publication date: 26/01/2023

Date of decision: 16/01/2023