Proposed Replacement Depot Turnpike Close Grantham
- Share this item
Meeting: 11/09/2023 - Cabinet (Item 23)
23 Proposed Replacement Depot Turnpike Close Grantham
PDF 373 KB
Cabinet is asked to consider the proposals and agree next steps to enable the development of a new depot at Turnpike Close in Grantham.
Additional documents:
- Appendix 1 - Site Plan, item 23
PDF 4 MB
- Appendix 2 - Business Case - March 2021, item 23
PDF 3 MB
- Appendix 3- Proposed Site Plan, item 23
PDF 2 MB
- Appendix 4 - Order of Cost, item 23
PDF 710 KB
- Webcast for Proposed Replacement Depot Turnpike Close Grantham
Minutes:
Purpose of report
To consider the proposals and agree the next steps to enable the development of a new depot at Turnpike Close in Grantham.
Decision
To recommend to Council:
1. That an allocation of £8million be included in the General Fund Capital Programme to provide funding to construct a new depot at Turnpike Close, Grantham.
2. A delegation of authority to the Council’s Section 151 Officer, in consultation with the Leader and Deputy Leader of the Council, to allocate further funding if required due to unforeseen costs during the project.
3. A request that the Finance and Economic Overview and Scrutiny Committee adds the replacement depot to its work programme and establishes a working group to receive regular updates and monitor the project.
Alternative options considered and rejected
Option 1 - To do nothing, not approve the budget for the construction of a new depot and remain at Alexandra Road. This had been discounted due to the growth of the District as identified in the Local Plan and the inability of the existing site to meet growth demands.
Option 2 – Investigate whether Alexandra Road (under the ownership of South Kesteven District Council) could be re- modelled to reconfigure the site.
Option 3 – Sell the Turnpike Close site and look for another site to purchase.
Reasons for decision
The site was chosen and purchased as the ideal situation for a replacement depot. The costs for the scheme were volatile but the building of the site was a priority due to potential changes in the Environment Act.
The Council needed to find an alternative provision for delivering its statutory function of this service. The site at Alexandra Road was geographically constrained and therefore could not accommodate any further service growth to meet future operational needs as identified in the Local Plan.
The welfare facilities did not meet modern standards for the Council’s workforce. A new facility would provide drying areas, new locker provisions as well as canteen and training facilities. The training room could be used by officers and Members providing a multipurpose space.
The ability to maximise sustainable systems so that the operational cost of the facility was lower showed a progressive approach working towards a carbon reduction target of 30% by 2030 and zero carbon by 2050.
The Leader of the Council and Cabinet Member for Property and Public Engagement highlighted several key points on the depot:
· An options appraisal on the Alexandra Road site still needed to be undertaken.
· The Lincolnshire County Council waste recycling centre must remain on the Alexandra Road site until at least April 2025 so as not to disrupt crucial services.
· The priority of delivering a new depot was highlighted in the Corporate Plan when it was being drafted in 2020, under the priority ‘building a fit for purpose depot’. The current site was not fit for purpose and had no capacity for key areas such as welfare facilities and the workshop to expand into.
· The Design team had worked on plans ... view the full minutes text for item 23