| No. | Item |
|---|---|
|
Public Open Forum
The Cabinet welcomes engagement from members of the public. To speak at this meeting please register no later than one working day prior to the date of the meeting via democracy@southkesteven.gov.uk Additional documents: Minutes: There were no questions or statements from members of the public. |
|
|
Apologies for absence
Additional documents: Minutes: There were no apologies for absence. |
|
|
Disclosure of Interests
Additional documents: Minutes: There were no declarations of interests. |
|
|
Minutes of the previous meeting
Minutes of the meeting held on 3 June 2025. Additional documents: Minutes: The minutes of the meeting held on 3 June 2025 were agreed as a correct record. |
|
|
Wharf Road Multi-Storey Car Park Grantham Phase 1 Maintenance Works
To obtain authority to enter in to a contract
of works for remedial works at Wharf Road Multi Storey Car Park in
Grantham Additional documents: Minutes: Purpose of report
To obtain authority to enter into a contract for essential maintenance works at Wharf Road Multi-Storey Car Park Grantham.
Decision
That Cabinet approves the award of a contract to Rio Asphalt & Paving Co Ltd for a value of £283,305.14 +VAT for essential maintenance works at Wharf Road Multi-Storey Car Park Grantham.
Alternative options considered and rejected
Delaying the works further would mean the car park surface and underlying concrete framed structure would further deteriorate leading to much higher costs in the future. Therefore, this option was discounted.
Reasons for the decision
|
|
|
Contract award for Structural Surveying & Associated works
To seek approval to enter into a contract with Millward Partnership for the provision structural surveys and associated works to Council owned dwellings for South Kesteven District Council. Additional documents:
Minutes: Purpose of report
To seek approval to enter into a contract with Millward Partnership for the provision of structural surveys and associated works to Council owned dwellings for South Kesteven District Council.
Decision
That Cabinet approves the award of a contract to Millward Partnership for the provision of carrying out structural surveys and associated works at South Kesteven District Council owned dwellings with an annual value of £50k for a period of 3 years with the option to extend annually for up to 2 years.
Alternative options considered and rejected
Consideration had been given to the option of carrying out the works “in-house”, but due to the specialist nature of the work this was not a viable option.
Not carrying out the work was also not practicable as this would have led to further building defects, increased repair costs and a housing stock with a low market value.
Reasons for the decision
Structural surveys enabled building defects to be investigated, and remedial work identified. The associated works included the provision of structural calculations along with specifications/drawings when required. All surveying and associated works that would be undertaken on the Council’s housing stock would be done to meet the industry standards and requirements that were set out by the relevant governing bodies. This ensured that residents had a safe home.
Typically, around 45 structural surveys and 12 associated projects were carried out each year. The annual cost for this service was anticipated at £50,000 per annum. The survey works would be funded from the structural survey revenue budget and the associated works would be met from the Technical Services Structural Refurbishment capital budget. The procurement opportunity was tendered as a mini competition using a framework run by Efficiency East Midlands (EEM). Following publication of the opportunity eight Expressions of Interest were received which resulted in four Tender Submissions.
After the tender exercise and evaluation, Millward Partnership gave the best tender submission through the combination of price and quality to carry out structural surveys and associated works on the Council’s housing stock. This ensured the Council had a contract in place which was compliant with procurement requirements. Dedicated staff trained in contract management would follow the performance clauses in the contract closely. |
|
|
Contract award for Gas and Electrical Auditing
To seek approval to enter into a contract with Morgan Lambert for the provision of carrying out gas and electrical auditing to Council owned dwellings for South Kesteven District Council. Additional documents: Minutes: Purpose of report
To seek approval to enter into a contract with Morgan Lambert for the provision of gas and electrical auditing to Council owned dwellings for South Kesteven District Council.
Decision
That Cabinet approves the award of a contract to Morgan Lambert for the provision of carrying out gas and electrical auditing in South Kesteven District Council owned dwellings, with an annual value of £50k for a period of 3 years with the option to extend annually for up to 2 years.
Alternative options considered and rejected
Consideration had been given to the option of carrying out the work in-house, but this was not a viable option due to the specialised nature of this work and third-party assurance required.
Not carrying out the work was also not practicable as this would have led to further issues as noted above. Carrying out this service by means of a third party ensured impartiality was maintained ensuring a fair and transparent service.
Reasons for the decision
Audits were undertaken on a sample of the gas and electrical works completed each month which provide assurance regarding the quality of the works. The annual cost for this service was anticipated at £50,000 per annum and would be met from the Technical Services Gas and Electrical capital budgets.
The procurement opportunity was tendered as a mini competition using a framework run by Efficiency East Midlands (EEM). Following publication of the opportunity five Expressions of Interest were received which resulted in two Tender Submissions.
Morgan Lambert have given the best tender submission through the combination of price and quality to carry out gas and electrical auditing on the Council’s housing stock and to ensure the Council has a compliant contract in place which is compliant with procurement requirements.
The contract award was for the auditing of gas and electrical works rather than for gas and electrical inspections. This award allowed a separate company to audit Council work. |
|
|
Local Government Reorganisation (LGR) Update
An update on the latest position with LGR in
light of the Interim Proposal Feedback letter Additional documents:
Minutes: Purpose of report
An update on the latest position with Local Government Reorganisation (LGR) following receipt of the Interim Proposal Feedback letter.
Decision
That Cabinet:
Alternative options considered and rejected
The Council had no obligation to submit an LGR proposal to the Ministry of Housing, Communities and Local Government (MHCLG). There would be no legal penalty for not doing so, but the Government stated that LGR would proceed even if no proposal was submitted. If the Council does not submit a proposal, it would lose the opportunity to shape and influence LGR to deliver on the strategic interests of South Kesteven’s residents.
Reasons for the decision
LGR would have a significant impact on the residents of South Kesteven; therefore, an update on the developing policy programme was presented. A robust LGR proposal must be high quality, evidence-based and offer a thorough analysis of the various options to detail the impact of the Council’s preferred LGR configuration on residents, services and businesses. Whilst the Council would endeavour to do as possible internally and with partners, it was recognised that some external expertise and support would add value.
A feedback letter from MHCLG had been received on 3 June 2025 regarding South Kesteven’s interim LGR proposal. Furthermore, in-person feedback was received from senior MHCLG officials on 2 and 4 July 2025. Both sets of feedback was general to the Greater Lincolnshire area rather than specific to the South Kesteven bid. MHCLG did not indicate a view on the merits or the features of the proposals submitted, which would have been useful for SKDC officers and members.
None of the proposals within Lincolnshire had been ruled out at this stage, which meant that the inclusion of Rutland County Council in a new authority remained an option. Any proposal would need to set out clear rationale for its findings.
A population of 500,000 was a guiding principle and not a strict target. Criteria are not weighted. Decisions would be judged in the round having regard to guidance and available evidence.
Government funding of £357,000 had been allocated to Greater Lincolnshire to support full proposal development. The Council would continue to work collaboratively to develop a full proposal for LGR that was the most beneficial – short, medium and long term - for both the residents and businesses of South Kesteven, and the wider geography of Greater Lincolnshire and Rutland County Council.
The Chief Executive, Portfolio Holder for Planning and the Leader of the Council all attended the Local Government Association (LGA) Conference last week. Much discussion was around LGR and how it might play out. The Leader spoke to other Leaders, Councillors and officers from across the country (and Lincolnshire). Those present ... view the full minutes text for item 19. |
|
|
Appointment of the Member Responsible for Housing Complaints
To approve the appointment of the Member
Responsible for Housing Complaints Additional documents: Minutes: Purpose of report
To approve the appointment of the Member Responsible for Housing Complaints.
Decision
That Cabinet approve the appointment of Councillor Virginia Moran, Cabinet Member for Housing, as the Member Responsible for Housing Complaints (MRC).
Alternative options considered and rejected
The Council could have chosen not to appoint an MRC but this would potentially lead to a breach of the Housing Ombudsman’s Complaint Handling Code.
Reasons for the decision
The Cabinet Member for Housing was appointed as the MRC as this ensured compliance with the Housing Ombudsman’s Complaint Handling Code. The Ombudsman did not recommend a term in advance of three years for the MRC.
The MRC would be able to seek support from the relevant officers. Any complaint involving the Cabinet Member for Housing would be considered by the Leader of the Council.
The Cabinet Member for Housing would receive training for this new role. |
|
|
Number of Dogs on Leads- PSPO Consultation
To give due consideration to consultation
responses received in November/ December 2024, which invited local
people, animal welfare organisations and businesses (which provide
services for dog owners), for their opinions on whether there is
need for a Public Spaces Protection Order (PSPO) which would limit
the number of dogs on leads that one person can walk at the same
time. Additional documents:
Minutes: Purpose of report
To give due consideration to consultation responses received in November/December 2024, which invited local people, animal welfare organisations and businesses (which provide services for dog owners), for their opinions on whether there was a need for a Public Spaces Protection Order (PSPO) limiting the number of dogs on leads that one person can walk at the same time.
Decision
That Cabinet notes the results of the public consultation and report.
Alternative options considered and rejected
It may have been deemed as unlawful to ignore the majority response, and re-consult with a view to putting a PSPO in place, as there was no evidence to support the need for this PSPO.
The consultation demonstrated there was not broad support regarding the implementation of a PSPO that would limit the number of dogs on leads that one person could walk at the same time. Therefore, it was requested that no further action was taken at this time.
Reasons for the decision
The purpose of the consultation was to ask local people, animal welfare organisations and businesses (which provide services for dog owners), for their opinions on whether there was a need for a PSPO which would limit the number of dogs on leads that one person could walk at the same time. The consultation demonstrated no broad support regarding the implementation of this proposed PSPO.
On 10 September 2024, Cabinet approved an immediate consultation for PSPOs concerning a recommended maximum number of dogs on leads per person. PSPOs were introduced by the Anti-Social Behaviour (ASB), Crime and Policing Act 2014 to deal with nuisances or problems that were detrimental to local quality of life. These imposed conditions on activity in specific areas applicable to everyone. PSPOs could be issued for any public space and were intended to ensure the law-abiding majority could use and enjoy public spaces, without suffering from anti-social behaviour. The definition of public space was wide and included any place to which the public or any section of the public had access.
The consultation was carried out late in 2024 and received 736 responses.
The following information was highlighted during debate:
|
|
|
Provisional Outturn 2024/25 - Budget Carry Forwards
This report seeks a delegation to enable budget carry forwards to be approved from the financial year 2024/25 to the financial year 2025/26. Additional documents: Minutes: Purpose of report
This report sought a delegation to approve the carry forward of budgets from financial year 2024/25 to financial year 2025/26.
Decision
That Cabinet delegated authority to the Deputy Chief Executive and Section 151 Officer, in consultation with the Cabinet Member for Finance, HR & Economic Development, to finalise the 2024/25 budget carry forwards for Capital and Revenue expenditure in respect of the General Fund and Housing Revenue Account (HRA).
Alternative options considered and rejected
An alternative option would have been to present the budget carry-forwards to a later meeting of Cabinet; however, this would have created a delay in the availability of budgets which would have a consequent detrimental impact on the delivery of the Council’s projects and services.
Reasons for the decision
Work was underway to prepare the outturn position of the Council for the financial year ending 31 March 2025. Alongside the preparation of the outturn, work was also underway to prepare the draft Statement of Accounts which would be subject to audit over the coming weeks.
It was a normal and regular activity and a key part of outturn preparations to consider and review budget carry forward requirements. These were budgets allocated for a financial year but the anticipated date of expenditure had been delayed into the following financial year. This was a normal occurrence that happened each financial year following the review of the outturn and where specific projects or events cross over financial years.
Due to unforeseen delays in compiling financial information, it had not been possible to present the budget carry forwards to the July meeting of Cabinet. To avoid deferring the decision until the September meeting, a delegation of authority to the S151 Officer in consultation with the Cabinet Member for Finance, HR and Economic Development was agreed to approve the budget carry forwards when they have been reviewed. Upon submission of the budget carry forward proposals, an Officer Delegation Decision Notice would be published to confirm the carry forwards that had been approved. |
|
|
Use of Pesticides on Council Land
To consider a recommendation from a joint
meeting of the Environment and Rural and Communities Overview and
Scrutiny Committees following a Motion to Council to eliminate the
use of pesticides on Council land. Additional documents: Minutes: Purpose of report
To consider a recommendation from a Joint Meeting of the Environment and Rural & Communities Overview and Scrutiny Committees following a motion to Council to eliminate the use of pesticides on Council land.
Decision
In noting the recommendations made by the Joint Meeting of the Environment and Rural & Communities Overview and Scrutiny Committee (OSC) on 4 March 2025 Cabinet resolved to:
Alternative options considered and rejected
A range of alternative options for controlling weed growth across the district were presented to the meeting of the joint OSC on 4 March 2025. There was consensus that none of the options identified were a suitable alternative.
Reasons for the decision
As detailed within the body of the report the Council’s use of glyphosate was already low relative to the size and rurality of South Kesteven district. The Council had already adopted a strategy of reducing its use as far as practical.
237 sites were sprayed within SKDC, which included several Housing Revenue Account (HRA) sites. In SKDC’s parks a diluted spray was used on paths and hard surfaces; nothing was used around mature trees or flower beds. Work around roadside verges was often contracted to Lincolnshire County Council.
The Cabinet Member for Environment and Waste has listened to the views of the Joint Environment and Rural & Communities Overview and Scrutiny Committees, as well as the proposer of the original motion, and had reviewed case studies and best practice. There had been no significant complaints related to the Council’s use of glyphosate.
Glyphosate was used carefully and in a targeted way; for example, it would be used to target weeds around newly planted trees. The resolutions brought SKDC into line with the approach taken by the Woodland Trust.
£490 was spent on glyphosates in 2023/2024, and not all this stock was used. Any alternative approach to tackling weeds without the use of glyphosate (where it was required) would cost at least £50,000, and this would potentially include an extra 2-4 members of staff and an extra 1-2 vehicles.
The following points were highlighted during debate:
|
|
|
Cabinet Forward Plan
This report highlights matters on the Cabinet’s Forward Plan. Additional documents: Minutes: The Cabinet Forward Plan was noted. |
|
|
Open Questions from Councillors
Additional documents: Minutes: Question One – Councillor Ian Selby to the Cabinet Member for Property and Public Engagement
Councillor Selby asked the Cabinet Member to discover for himself how accessible the Grantham Meres Stadium was, whilst asking him to take note of its dilapidation. He requested it be part of ideas for the future.
The Cabinet Member was happy to look into this issue.
Question Two - Councillor Rhea Rayside to the Cabinet Member for Housing
Councillor Rayside asked whether there were any best practices from other councils SKDC could adopt to ensure a proactive rather than reactive approach to those that walk too many, or an unmanageable number of dogs.
Councillor Moran asked for the issue to be re-visited in a year’s time to have a look at the number of issues or incidents.
The Cabinet Member for Property and Public Engagement was happy to investigate joint publicity campaigns with Lincolnshire Police on this issue.
The meeting closed at 3:53pm. |