Agenda item

Application S20/1192

Proposal:                  Erection of 14 industrial units including storage, warehouse and associated works.

Location:                   The Bungalow Northfield Road Market Deeping Lincolnshire PE6 8LG

Recommendation:     That the application is approved conditionally

 

Minutes:

Proposal: Erection of 14 industrial units including storage, warehouse and

associated works.

 

Location: The Bungalow Northfield Road Market Deeping Lincolnshire PE6 8LG

 

Decision: That the application is approved conditionally.

 

Noted:

 

·       Provisions within the National Planning Policy Framework and the South Kesteven Local Plan and supplementary planning documents

·       Site observations

·       Site had permission granted to planning application Ref: S19/1106

·       No objection or observations from Heritage Lincolnshire

·       No objection from Anglian Water Subject to foul water drainage

·       No objection from Market Deeping Town Council other than restrictions on use of Class B and operating hours.

·       No objection from Lincolnshire County Council Highways and SuDS

·       Representations as a result of publicity

 

It was proposed, seconded and agreed unanimously that the application be

approved for the summary of reasons set out in the case officer’s report and

subject also to the following conditions:

 

Time Limit for Commencement

 

1.    The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.

 

Approved Plans

 

2.    The development hereby permitted shall be carried out in accordance with the following list of approved plans:

 

i.      Site location plan received 20th July 2020

ii.     308/P/104 Rev A received on 20th July 2020

iii.    308/P/105 recieved on 20th July 2020

iv.   308/P/100 Rev C received 27th October 2020

v.     100 Rev P2 received 20th July 2020

vi.   101 Rev P2 received 20th July 2020

 

Unless otherwise required by another condition of this permission.

 

During Building Works

 

3.    Prior to the construction above damp-proof course, a scheme for on-site foul water drainage works, including connection point and discharge rate, shall be submitted to and approved in writing by the Local Planning Authority. Prior to the occupation of any phase, the foul water drainage works relating to that phase must have been carried out in complete accordance with the approved scheme.

 

4.    Before installation of any external plant, final details of the position, type, external appearance, noise emissions and shall have been submitted to and approved in writing by the local planning authority.

 

Before the Development is Occupied

 

5.    Before the end of the first planting/seeding season following the first use of any part of the development hereby permitted, all soft landscape works shall have been carried out in accordance with the approved soft landscaping details on drawing no. 308/P/105.

 

6.    Notwithstanding details on the approved plans, before first occupation of the units hereby approved, details of a vehicular and pedestrian link to land to the west of the site together with a timetable of implementation must be submitted and approved by the Local Planning Authority.

 

The approved details should be implemented in accordance with the agreed timetable.

 

7.    Before any part of the development hereby permitted is brought into use, all hard landscape works shall have been carried out in accordance with the approved hard landscaping details on drawing no. 308/P/100 Rev C.

 

8.    Before any part of the development hereby permitted is brought into use, the external elevations shall have been completed using only the materials stated in the planning application forms.

 

Ongoing Conditions

 

9.    No external lighting other than the details approved in the B and H Services Group Ltd document dated June 2020 shall be installed unless they have been first submitted to and approved in writing by the local planning authority.

 

10. Within a period of five years from the first occupation of the final unit of the development hereby permitted, any trees or plants provided as part of the approved soft landscaping scheme, die or become, in the opinion of the Local Planning Authority, seriously damaged or defective, shall be replaced in the first planting season following any such loss with a specimen of the same size and species as was approved in condition above unless otherwise agreed by the Local Planning Authority.

 

11. Noise from operations conducted on the premises shall not exceed 55 dBa Leq 1 hour, as measured at the boundaries of the application site, between the hours of 0700 and 1900 on Mondays to Fridays and 0700 and 1200 on Saturdays, and 45 dBa Leq 1 hour at any other time.

 

12. Notwithstanding the provisions of Schedule 2, Parts 3 and 4 of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking or re-enacting that Order with or without modification), the premises shall only be used for the purposes specified below and for no other purpose unless Planning Permission for a new use of the premises has been granted by the Local Planning Authority:

 

- Use permitted by Classes B1/E(g) only and B8 of the Town and Country Planning (Use Classes) Order 1987 (as amended)

 

13. Following the development hereby permitted first being brought into use, the vehicle parking and turning areas shall have been completed in accordance with approved drawing no. 308/P/100 Rev C; and shall not be used for any purpose other than for the parking and turning of private vehicles and motorcycles belonging to the occupants of the property and their visitors.