Budget Report for 2026/2027 including Indicative Budgets for 2027/2028 and 2028/2029 - General Fund

Minutes:

Purpose of report

 

To present the draft budget proposals and estimates for 2026/27 for the General Fund.

 

Decision

 

Cabinet made the following recommendations to Council:

 

1.     Set a General Fund budget requirement of £22.875m for 2026/27 inclusive of Special Expenses (Section 3 and Appendix A of the report).

 

2.     Propose a Council Tax level of £195.03 including Special Expenses for 2026/27 (Band D property) after consideration of the consultation responses.

 

3.     Note indicative Budget estimates for 2027/28 and 2028/29 (Appendix A of the report).

 

4.     Approve the General Fund Capital programme and financing statement 2026/27 to 2028/29 (Section 6 and Appendix B of the report).

 

5.     Approve the General Fund Capital Programme budget carry forward £1.389m from 2025/26 (Appendix B).

 

6.     Approve the movements in General Fund Reserves (Section 8 and Appendix C of the report).

 

7.     Approve the Treasury Management Strategy Statement (Section 9 and Appendix F).

 

8.     To approve the Capital Strategy (Section 9 and Appendix G of the report).

 

Other options considered

 

The alternative options were considered throughout the report.

 

Reasons for the decision

 

The Council was required to set a balanced budget each financial year.

 

At Joint Budget OSC it was highlighted that the Government has completed their fair funding review. For SKDC this resulted in a multi-year settlement to 2028/2029. Whilst this provided some financial certainty, the Government has said that the latter two years may be subject to a future reassessment.

On 9 February 2026 the final settlement was confirmed by Government  outlining that an element of business rate funding was being taken away from some local councils. The Government had committed to offsetting this loss to SKDC in 2026/2027 through an ‘Adjustment Support Grant’. It was unclear whether this Grant was a one-off payment or would continue into future years. Without the Grant, the forecasted Budget for 2027/2028 would contain a deficit position.

 

In January 2026 SKDC launched their Council Tax consultation with residents. 61% of respondents supported the Council’s proposals to increase Council Tax by 2.99% (£5.66 increase on a Band D property). This was an increase on the 55% support seen in the previous year’s consultation.

 

A balanced budget had been achieved. Within this, £20,000 would be committed towards the ‘Newton 300’ celebrations, earmarked from the £100,000 events budget. Once the budget outturn position was known, it was likely that the £100,000 budget would be replenished. Funding for the district’s market towns had also been made available.

.

There was a debate about fees associated with houses in multiple occupancy (HMOs) at Full Council on 29 January 2026. A ‘sliding scale’ of fees had been discussed; officers have since looked again at staffing resources in relation to HMOs, as well as benchmarking against other local authorities. A proposal would be brought back to Full Council on 26 February 2026.

 

Proposed recurring budget increases were:

 

Heading

Cost

Details

Employee Expenditure

£316,060

• Enforcement Officer

• Private Sector Housing Officer

• Events Officer

• Income Recovery Officer

• Rough Sleeper Support Officer Roles

• Housing Options Officer

Tree planting for SKDC open spaces

£62,000

Tree planting initiative across the District including in the award-winning parks

Tree maintenance for SKDC open spaces

£66,150

Allocation to respond to the actions arising from the Tree Management Policy

Events budget

£100,000

A programme of public events across the district during 2026/27. The programme to be presented to the Leisure and Culture OSC.

Funding for Compliance Works in General Fund Corporate Buildings

£100,000

Rolling programme of compliance works relating to DDA, Asbestos, Fire Risk Assessments across General Fund assets

Surface Water Drainage Clearance Programme

£60,000

Rolling programme of remedial repairs and maintenance of gullies and drainage systems.

Stock condition surveys

£40,000

Rolling programme of stock condition surveys across General Fund assets. 20% of assets to be surveyed each year

Increase in community grants

£100,000

Increase in the annual budget for the established community grant scheme from £100k to £200k

Total

£844,210

 

 